Human-Machine Interfaces(HMIs)-GOT GOT2000 Series
Startup/adjustment
Operation command
- CASE1
- CASE2
- CASE3
- CASE4
- CASE5
GT27
GT25
GT23*2
GT21*2
GS21*2
SoftGOT*2*3
Challenge
We want to start up the system while confirming the inverter's operation!
Solutions
Issue operation commands to the inverter from the GOT
The inverter operation commands can be issued from the GOT. Since the system operation can be confirmed while monitoring the inverter's output frequency and output current values, the startup work efficiency can be increased.
- *1Sample screens (VGA) are available. The screen image is the sample screen of FR-A800-E for CASE 1. The screen image differs from the one for FR-E800 and CASE 4.
- *2Sample screens are not supported by GT23, GT21, GS21, and GT SoftGOT2000.
- *3Supported by GT SoftGOT2000 (Multiple channels) only.